Current Status - Almost Done
1/5 - FCP installed technology checked and ready to go. Need shock alarm on Mac from Barry. Take over headsets.
12/27 - Need to see that FCP has been installed by Andy and shock alarm installed by Barry.
Get headphones back from Jennifer and set up in here and 48. Signage?
12/22 - Sensory installed camera and mics. I was able to test out the system before they left and everything was working fine. Had to spend some time tweeking the sound mixer but it's all good now.
12/21 - iMac installed and set up. Checked projection, audio, ran some updates. Will let Andy know he needs to install FCP on this computer.
Mentioned the need for shock alarms in this room (one for iMac) and FB110 (two) to Barry. He will order more.
Spoke to Andy about loading FCP on this computer. It's already loaded on the two laptops in the back of JH048.
12/15 - Dec 22 is the date planned for Sensory to install in this room
12/10 - Mac to be delivered to this room and left in the corner. Room is available after 12/16 for us to set up Mac and move PC back to JH037. Julianne signed and delivered PO to Earl